Start construction concrete deck, Ingelmunster (BE) - (March 26, 2019)

On the 20th of march the first and biggest pouring phase of the concrete deck of the Ingelmunster bridge was complete. In total 618 m³ concrete was poured on a specially designed self-supported formwork hanging on the steel girders. Three more pouring phases, of 420, 170 and 215m³, will be needed to finish the complete deck.